Major steel bridge "Akaski Kaikyo Bridge" and details of structural steel members utilized for construction with their specifications and features
Introduction to Akaski Kaikyo Bridge:
Facts
of Akashi Kaikyo Suspension Bridge:
- The
bridge is so long, it would take eight years Towers laid end to end to
span the same distance.
- The
length of the cables used in the bridge totals 300,000 kilometres. That's
enough to circle the earth 7 times!
- The
bridge was originally designed to be 12,825 feet. But on January 17, 1995,
the Great Hanshin Earthquake stretched the bridge an additional three
feet.
- The
bridge holds three records: it is the longest, tallest, and most expensive
suspension bridge ever built.
- Over
2 million workers, billions of dollars, 181,000 tons of steel and 1.4
million cubic meters of concrete were used in its construction
- Its
foundation is as deep as a 20 storey apartment blocks, towers almost as
tall as the Eiffel towers in Paris.
- Its
span is nearly 2 km (1/3 times more than any other suspension bridge built
ever before)
- Theory
of suspension bridge design
- Two
main cables suspended across the water, held up by two towers
Statistics
/ Facts:
- Location: Kobe and
Awaji-shima, Japan
- Completion Date: 1998
- Cost: $4.3 billion
- Length: 12,828 feet
- Type: Suspension
- Purpose: Roadway
- Materials: Steel
- Longest Single Span: 6,527
feet
- Engineer(s): Honshu-Shikoku
Bridge Authority
v On
identifying one of the major steel
bridges namely “Akashi Kaikyo Suspension Bridge” I have found the following
structural members that were involved in its construction:
1. 1. The Main Cables
2. 2. Pylons
3. 3.Stiffening Girder
4. 4. Anchorages
5. 5. Connections: Hangers
& Cable Bands
ü Specifications and features of Structural Members
utilized for the construction of the bridge:
The main cables run from anchorage to anchorage. A cable is composed of
a number of strands. These strands can be made in situ by cable spinning or
they are prefabricated. The number of strands builds up in a simple arithmetic
progression. The cable thus consists of a central strand surrounded by 6 strands,
6 + 12 strands, 6 + 12 + 18 strands, etc.
The cable in Figure 4 contains 37 strands and this is a common number in
bridges with spun cables. (The numbers indicate the sequence of spanning the
individual strands.) Thus, in the Humber Bridge the main cables are composed of
37 strands: each having 404 wires.
In bridges with main cables made of parallel wire strands, the number of
strands is generally higher as each strand has to contain fewer wires for
reasons of handling.
Before starting the main cable erection, a catwalk is made, running from anchorage to anchorage via the pylon tops. A tramway is mounted on this catwalk if the cables are to be spun. The tramway is not necessarily required for the transport of prefabricated strands. To protect the catwalk to some, extend against the wind, a pretensioning system of counter parabolas is used.
The essentials of the cable spinning
process are shown in Figure 5. The catwalk and tramway are indicated. Two
spinning wheels, connected to a loop, carry separate wires from one side to the
other. At one of the anchors blocks the dead wire is fixed. On the other side
the wire is taken off the spinning wheel and looped around a strand shoe
(Figure 6). Next the live wire is fixed. When a strand, consisting of 300 to
400 wires, is finished, this strand is located carefully in its correct place.
This operation is carried out at night when the temperature is nearest to
uniform.
The optimum wire diameter is 5,0-5,5mm. A larger diameter makes the wire
too stiff, while a smaller diameter requires more wires and more labour. The
wire material has an ultimate strength up to 1600 - 1800N/mm2.
With span cables, each working shift can mount about 160 wires a day,
and in most cases two shifts per day per cable is used. Prefabricated strands
can be mounted in a shorter period.
After having erected all wires the bundle of strands are compacted into
a circular shape. As a protective treatment, the cable is finally wrapped with
a mild steel wire. During this wrapping a protective paint is added.
Where the cable passes over the pylon tops and the splay saddles, they
lose their circular shape. Special provision is necessary at these locations to
keep corrosion under control.
Technical features of
cable
The foundation of the pylon is a concrete massive slab with base
dimensions of 67.4 x 28.0 m and thickness variable from 2.5 to 6.5 m, placed on
160 reinforced concrete piles, 18.0 m long of 1.5 m diameter. The piles were
drilled in drawn steel tubes with cement injection of the base. It was assumed
that both the piles and the soil under the foundation slab were load carrying
element. The pylon’s structure is hybrid (Fig. 3): - the pylon’s legs and the
lower parts of the arms are made of reinforced concrete; - the upper part of
the arms is a hollow composite structure; - the lower crossbeam is a
post-tensioned concrete element; - the upper crossbeam is a post-tensioned
steel-concrete box structure. Inside the pylon, a steel core, presented in Fig.
3, was placed. It formed the inner formwork during erection of the pylon and it
interacts with the reinforced concrete shell, transferring vertical forces and
bending moments. In the cable anchorage zones the core carries horizontal
forces transmitted to the walls of the pylon by cable stays. The steel core and
the reinforced concrete shell act as a composite section due to shear studs
welded to the core’s side plates. An important load carrying element of the
pylon is the upper crossbeam (compressed and torsioned). It was vertically and longitudinally
post-tensioned, and heavily reinforced (Fig. 4).
It should be considered that there are many factors influencing the
choice of the material for pylons, e.g. soil conditions, speed of erection,
stability during their construction, etc. Therefore, the choice should not be
based entirely on a quantity-based cost estimate.
Functions of Tower/Pylon of Cable Suspension Bridge or Cable Stayed Bridge:
The main function of tower of cable stayed bridge was to safely support bridge loads and traffic loads. Towers should be aesthetically pleasing and demonstrate satisfactory survivability performance. Figures shows free body diagram of suspension bridge and cable stayed bridge and illustrates how towers support bridge loads and traffic loads.
3. Stiffening Girder
The choice of the cross-section for the stiffening girder is a very
important step, since this influences the behaviour of the total structural
system.
The developments in girder design have been closely connected to the
development of calculation methods, in particular the deflection theory which
is especially relevant for lighter girders.
Technical Features of Stiffening Girder:
To determine the type of the stiffening
girder, several types of girders as shown in Fig. 5 were investigated. Fig. 5
also shows the relationships between the onset wind speed of flutter and deck
weight for the investigated girders. From these results, the truss girder and
compounds stiffness box girder were selected as prospective types. The compound
stiffness box girder is a bridge system that arranges
high-tortionally-stiffened girders around the tower and aerodynamically-well
flat girders at the central portion of the bridge. From the comparison of these
two types of girders, truss was finally selected due to its ease of its
erection on the international navigation channel, because the erection of the
truss can be done by not using the navigation channel.
The dynamic behaviour of suspension bridges due to the wind has been
investigated mainly by wind tunnel tests using sectional models so far. For the
Akashi Kaikyo Bridge, however, a full model test in a large wind tunnel
facility was required for the following reasons. 1 The deflection of the bridge
due to wind is large. 2 Along the bridge axis with the length of 4 km, there is
a large variation of wind properties. 3 The effect of the main cables cannot be
neglected. 4 The effect of the turbulent flow cannot be neglected. Therefore,
we built a large boundary layer wind tunnel facility with width of 41m, height
of 4 m, and length of 30 m. As a result of the experiment of a scale of 1/100,
it was confirmed that the required wind resistance could be obtained by
installing some gratings on the road deck and a vertical stabilizing device
along the truss girder as shown in Fig. 6
Due to its flexible structure, vibration, especially flutter due to
wind, was the most important problem at the design stage of the stiffening
girder. In the design code, it is specified that flutter must not occur under
the wind speed of 78 m/s in the wind tunnel test within the attack angle from
-3 deg. to +3 deg..
The main cable force is composed of two components, the vertical trying
to lift the anchor block, and the horizontal trying to pull the anchor block
towards the centre of the bridge. The method of anchoring the main cable
depends largely on the local soil conditions.
In gravity anchorages equilibrium between the cable force and soil
pressure has to be carefully considered during erection. During erection the
vertical component of the cable force increases, exerting a vertical lifting
force on the anchorage. In order to limit the variations in soil pressure it
might prove advantageous to increase the mass of the anchorage in pace with the
erection. This procedure reduces subsidence problems and could make the
construction, in particular the foundation, cheaper.
5-Hangers and Cable Bands
Socketed hangers connect the main cable and girder.
The hanger is connected to the main cable via a cable band consisting of
two semi-cylindrical halves, connected together by high tensile steel bolts to
develop the necessary friction. The hanger is connected to this cable band via
a pin connection or it may be looped over the cable band.
The cable bands are firmly tightened onto the main cable and get their load carrying resistance mainly from friction and compression of the cable (Figure 17). The cable bands are carefully machined, taking into account an air void of approximately 20% in the cable.
The main cable is subject to an axial loading that increases during
erection of the bridge. The elongation of the cable from the anchor block to
the pylon should be taken into account, e.g. by giving the pylons a pull-back
(Figure 18).
For the cable bands, the transverse contraction of the cable section is of the utmost importance. It causes the friction between cable band and cable to decrease and, as a result, the load carrying resistance goes down. Precautions should be taken to measure the relaxation and to tighten the bolts during erection, e.g. by making a backlash (Figure 19). For reasons of maintenance, the remaining gap is filled with rubber. In view of the contraction, the cable wrapping should be carried out after the bridge carries almost all of its full dead load.
Vertical hangers are usual. For a period of about 15 years inclined
hangers were popular (Figure 20). The use of inclined hangers started with the
Severn Bridge (1966) and was concluded with the Humber Bridge (1981).
The idea was to make the bridge more rigid (» 25%), due to
the truss behavior, and to reduce the tendency to oscillate (flutter). The aim
was to increase damping by utilizing the hysteresis of the spiral wires forming
the hangers. However, the constantly changing forces in the hangers can create
fatigue problems, and this is one of the reasons why designers returned to
apply vertical hangers only.
By: Shaib Shabir
B.tech (Civil Engineering)
M.tech (Construction Technology & Management)
dar_shoaib_shabir













Comments
Post a Comment